Stalled Mau Mau road Lot 2 project contractor put on notice

Publicado em: 15/11/2026 00:25

The National Assembly Committee on Transport and Infrastructure has ordered the contractor undertaking the Mau Mau roads Lot 2 project to expedite construction works and ensure timely completion.

Speaking during an inspection tour of the Tuthu-Kanyenyaini road, which forms part of the Mau Mau roads Lot 2 project, the committee led by its chairperson George Kariuki noted that the government had already settled all payments due for the project.

They therefore ruled out any financial constraints as reasons for the unprecedented delays and stalling.

“We can confirm that the contractor has been paid in full, and we have directed the immediate redeployment of the workforce from the other ongoing projects to ensure that Kanyenyaini-Tuthu road construction is accelerated and completed within the stipulated timelines,” said Kariuki, who is also the Ndia MP.

National Assembly Transport and Infrastructure Committee Chair George Kariuki, member of the committee Twalib Badi and Kangema MP Peter Kihungi, when they addressed residents in the Kigumo area along the Tuthu-Kanyenyaini road in Kangema Constituency.

“The government is committed to ensuring that all the stalled projects  across the country are completed in record time in line with the president’s promises,” he said.

The Chairperson noted that after deliberations with the contractor, the committee had ordered him to have the construction works on the 20-kilometre Kangema-Karurumo road stretch commence in January 2027.

Committee member Twalib Badi, who is also the Jomvu MP, on his part assured the residents that the Mau Mau Roads Lot 2 project will be hastened to stimulate economic development in the agricultural-rich area of Kangema.

“You are basically dairy farmers, tea and avocado growers, and supporting infrastructure is a prerequisite for economic development. This road will be tarmacked just like we have started Jomvu-Mombasa Lot 1 and Jomvu Mariakani Lot 2 in honour of our independence heroes, so even here this Mau-Mau road project will be tarmacked without further delays,”  said Badi.

The Kangema MP Peter Kihungi concurs that the 13 km stretch has remained in a deplorable state since independence and has continued to inconvenience the residents while affecting their daily lives.

Kihungi urged the committee to ensure that the promise to tarmac the road is delivered without further delay.

He said they had agreed with area residents that no material or equipment shall be moved from that site until the road is tarmacked because it had already been budgeted and earmarked for construction.

“A while ago it was reported that materials and equipment were being relocated to construct roads in other areas, and the residents joined hands and rejected any site relocation until this Kanyenyaini-Tuthu road is tarmacked,” he noted.

Residents welcomed the move, noting that the construction would ease transportation, improve accessibility and boost their economic activities.

“We have received many promises before, yet our road remains impassable, but we are now hopeful that it will finally be tarmacked,” said John Kamau.

“Since I was born about 60 years ago, the 13 km stretch to Kanyenyaini has remained impassable, since no vehicles can access it,” he added.

Rhoda Njeri on her part notes that inaccessibility has affected their livelihoods due to reduced earnings and limited opportunities.

“Farming is our main source of livelihood, but even taking our farm produce to the market is an exercise in futility; recently our low tea earnings were even attributed to the inaccessibility of our region, as there is no road network.

We are, however, hopeful that the construction will finally begin, since even materials to construct roads in other areas are sourced from the locality, yet our own road remains in a deplorable condition,” she said.

By Florence Kinyua

Fonte: Kenya News